Hadley vs. Baxendale : Facts, Issues, Contentions, Judgement & Analysis

Hadley v Baxendale[1] is a landmark English caselaw that determines the consequences of loss to one party caused by the negligence of the opposite party in special circumstances.

Facts

  1. Hadley’s corn millwork came to a halt when his crankshaft broke, and he had to wait for it to be replaced. He had to ship the shaft to Joyce and Co., an engineering firm, so they could use it as a model for a new one.
  2. Hadley (Plaintiff) and Pickford and Co., a Baxendale (Defendant) owned and managed shipping company, agreed that if Hadley delivered the shaft to Pickford and Co. before noon the next day, Baxendale would transport the shaft to Joyce and Co. the following day.
  3. Hadley paid for the shipping services and delivered the shaft to Pickford and Co. before midday, as agreed but failed to inform Baxendale that his mill is inoperable without the shaft.
  4. Baxendale’s incompetence caused the shipping to be delayed, and the shaft was delivered several days after the agreed-upon date. Hadley’s mill remained closed as a result of Pickford’s breach until the new shaft arrived.
  5. Hadley retaliated by filing a lawsuit against Baxendale for damages. Hadley included the lost earnings his company suffered because of Pickford and Co.’s violation in his damages claim.

Issue

Is Defendant liable for Plaintiff’s damages that arose due to delay in shipment of the shaft?

Judgement

It was held that the defendant was not liable for the plaintiff’s losses. The damages flowing naturally from the breach or those in the reasonable contemplation of the parties at the time of contracting are available to the non-breaching party. While the defendant’s breach was the direct cause of the Plaintiffs’ lost earnings, such loss cannot be said to occur naturally from such a breach under normal circumstances. A miller may send a crankshaft to a third party for a variety of reasons. Defendants had no way of knowing that their breach would result in a longer mill outage and a loss of earnings. Furthermore, Plaintiff never informed Defendants of the unique circumstances, and Defendants were unaware of the unique circumstances.

Analysis of the Judgement

The rule of Hadley v Baxendale consists of two parts:

On breach of a contract such damages can be recovered:

  1. As may fairly and reasonably be considered arising naturally, that is, according to the usual course of things from such breach; or
  2. As may reasonably be supposed to have been in contemplation, of both the parties at the time they made the contract.

In either way, the resulting damage must be the probable result of the breach of contract.

Under the first rule, compensation can be claimed for any loss or damage that arose in the usual course of things the breach rooms of contract. If the loss does not arise in the usual course of things but is a special loss arising out of special circumstances, then the situation would be covered by the second branch of the rule. In that case, the last can be claimed if the same wasn’t contemplation of both the parties at the time of the making of the contract.

Under the second rule, if the loss on the breach of the contract does not arise naturally, that is, according to the usual course of things but it arises due to some special circumstances, the person making a breach of contract can be made liable for the same provided that those special circumstances go block to his knowledge at the time of the making of the contract. If he had no knowledge of the special circumstances which resulted in the particular loss, he cannot be made liable for the same.

Indian Position on Damages for Breach of Contract

In India, section 73 of the Indian Contract Act, 1872, makes the provision regarding the right of the injured party would it cover compensation for the loss or damage which is caused to him by the breach of contract. it reads as:

“When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it.

Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach.

Compensation for failure to discharge obligation resembling those created by contract—When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default, as if such person had contracted to discharge it and had broken his contract.

Explanation—In estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account.”

The provision contained in section 73 (para 1) is similar who the rule contained in the above-stated judgment of Hadley vs Baxendale.

Conclusion

The remedy of breach of contract is to prevent the injured party from loss caused by the other party. However, there are certain circumstances, where the defaulting party cannot fathom the consequences of their actions by using due diligence. The judgement acts as a precedent and protects them from such unforeseen circumstances.

[1] (1854) 9 Ex. 341

Leave a comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.